The following is the online version of the MAPCON User Manual for the software version indicated in the Table of Contents. The Manual provides a detailed description for the users of our CMMS including our CMMS Software, Maintenance Software and Preventive Maintenance Software operations and methodology. Please feel free to send us your comments via email.
Previous Page | Table of Contents | Next Page
Creating, Canceling or Editing a Work Order
The system allows two methods of creating or editing Work Orders and attaching them to the Project.
The first method should only be used for large Projects. In this method, data entry clerks who do not have Project authorization create Work Orders using the normal Work Order System. These Work Orders can then be attached to the Project at the Project Manager's convenience. The possible problem with this approach is that data can be entered incorrectly. For example, the Work Order cannot be attached if it is written against a Cost Center other than the Project's Cost Center.
In the second method, all functions are done by branching to the Work Order System from the Project Control screen. This is the recommended method as it allows all necessary data to be transferred automatically from the Project to the Work Order when it is created. This eliminates any possibility of input error.
To edit a Work Order, simply place the cursor on a Work Order Number, click on Options and the click on Edit or Create Work Order.
To create a Work Order, enter a W in the CD field and press Enter. The cursor should now be in a blank Ref# field. Click on Options and then click on Edit or Create Work Order. A new Work Order will be initiated with most of the data already entered.
Calculating Project Dates
Click on Re-calculate Dates to manually recalculate all Start and End Dates in the Project matrix.
Project Control Page - con't
Description - The Description field defaults to the Work Order's or imbedded Project's Description and can be changed to a description that is more related to the Project context.
Three display only fields follow: Status, Est. Start Date and Slack Days.
The Est. Start Date is always set to the Project Start Date for those Work Orders or Projects that have no predecessor(s). The Est. Start Date for Work Orders or Projects with predecessors is calculated once all of their predecessors have a Duration.
Previous Page | Table of Contents | Next Page
Learn more about MAPCON CMMS Software
Contact us today. Our primary preventive maintenance software products are MAPCON Jemms, MAPCON Pro and MAPCON Lite. We provide full support (a real human right here in the United States) and training both on-site or at our classrooms in Des Moines, Iowa.
Call us at 1-800-922-4336 or go right to our Downloads Page and select your solution!
To Top